Concurrent Delay: Who Keeps the Time, Who Pays for It
- KT.01In England, true concurrent delay does not reduce the contractor's extension of time: Walter Lilly settled the point and rejected apportionment.
- KT.02Time and money diverge. The concurrent period carries no loss and expense unless the contractor can separate the costs caused by the employer delay from those caused by its own.
- KT.03Concurrency risk can be reallocated by express terms. After North Midland, the first question is not what the law says but what the clause says.
Concurrent delay takes up more space in delay submissions than any other doctrine, and it is misapplied in most of them. The English position is settled and deliberately asymmetric: where employer delay and contractor delay are truly concurrent, the contractor keeps its extension of time in full, but it recovers nothing for the concurrent period unless it can separate the money. Who keeps the time and who pays for it are different questions with different answers.
What concurrency actually means
The working definition comes from Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32.¹ Dyson J recorded the parties' agreed position: if there are two concurrent causes of delay, one of which is a relevant event and the other is not, the contractor is entitled to an extension of time for the period of delay caused by the relevant event, notwithstanding the concurrent effect of the other. The example given was exceptionally inclement weather stopping the works for a week while the contractor was, in the same week, short of labour: one cause a relevant event, one not, both operative.
Two decades of refinement have sharpened the concept rather than changed it. The definition now most often adopted is John Marrin QC's: a period of project overrun caused by two or more effective causes of delay of approximately equal causative potency, a formulation endorsed by the Court of Appeal in North Midland. The qualification matters. True concurrency requires two effective causes operating at the same time, each independently sufficient to delay completion. Delays that are sequential, delays on different paths, and contractor delay that merely coexists with an employer event without driving completion do not qualify.
True concurrency is rare; asserted concurrency is everywhere.
Time: the full extension survives
Walter Lilly & Company Ltd v Mackay [2012] EWHC 1773 (TCC) settled the English position on time.² Akenhead J held, at [370], that where delay is caused by two or more effective causes, one of which entitles the contractor to an extension of time as a relevant event, the contractor is entitled to a full extension of time. There is nothing in the JCT machinery that permits the extension to be discounted because the contractor was also in culpable delay: the clause asks whether a relevant event caused delay to completion, not whether it was the only cause.
The result is not generosity to contractors. It reflects the structure of the bargain: the employer accepts the risk of the events it has designated as relevant events, and the contractor cannot be held to a completion date that the employer's own acts helped to make unachievable. The Society of Construction Law Delay and Disruption Protocol, 2nd edition (February 2017), adopts the same position at Core Principle 10: concurrent contractor delay should not reduce the extension of time due.⁶
Where delay is caused by two or more effective causes, one of which is a relevant event, the contractor is entitled to a full extension of time. Apportionment rejected as a matter of English law.
Read the sourceThe Scottish contrast
City Inn Ltd v Shepherd Construction Ltd [2010] CSIH 68 took a different road.³ The Inner House of the Court of Session held, by a majority, that where two causes of delay are concurrent and neither can be identified as dominant, the decision-maker may apportion the delay between them in a fair and reasonable way, treating the exercise as one of judgment rather than strict causation.
City Inn is regularly cited in English adjudications and just as regularly overvalued. It is a Scottish decision, persuasive authority at most, and Akenhead J expressly declined to follow it in Walter Lilly. Apportionment of an extension of time forms no part of English law. A tribunal invited to split a concurrent period sixty-forty on a contract governed by English law is being invited into an exercise the authorities do not sanction, and a responding party should say so plainly.
Where neither concurrent cause is dominant, delay may be apportioned between them on a fair and reasonable basis. A Scottish decision, expressly not followed in Walter Lilly; it does not represent English law.
Read the sourceMoney answers a different question
The extension of time protects the contractor from liquidated damages. It does not carry loss and expense with it. De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC) states the general rule: where there is concurrent delay to completion caused by matters for which both employer and contractor are responsible, the contractor is entitled to an extension of time but cannot recover in respect of the loss caused by the delay.⁴
The logic is straightforward causation. Loss and expense must be proved to have been caused by the employer event. If the contractor would have been on site for the same period in any event because of its own delay, the but-for test fails and the time-related loss is irrecoverable. Core Principle 14 of the SCL Protocol draws the same line: the contractor recovers compensation for a concurrent period only if it can separate the additional costs caused by the employer delay from those caused by its own.⁶ Untangling the compensable delay is not a pleading exercise; it is a records exercise, and it must be done head of loss by head of loss.
The contractor keeps the time. It does not, without more, get the money.
The general rule for concurrent delay: extension of time yes, recovery of delay loss no. Compensation requires the contractor to separate the loss caused by the employer event from loss it would have suffered in any event.
Read the sourceThe parties can contract out
All of the above is the default position, and North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744 confirmed that it is no more than that.⁵ The contract, a JCT Design and Build form with bespoke amendments, provided that any delay caused by a relevant event which was concurrent with a delay for which the contractor was responsible would not be taken into account in assessing the extension of time. The contractor argued that the prevention principle rendered the clause ineffective. Coulson LJ disagreed: the clause was “crystal clear”, the parties were free to allocate the risk of concurrent delay as they wished, and the prevention principle is not an overriding rule of public or legal policy capable of defeating express terms.
The practical consequence is that concurrency is now as much a drafting question as a legal one. Bespoke amendments to JCT and NEC forms routinely shift concurrency risk to the contractor, and some define concurrency so loosely that they capture delay which is merely sequential. The first task in any concurrency dispute is therefore not Walter Lilly but the contract itself: establish what the clause says, whether it adopts or displaces the default position, and how it defines the concurrency it purports to exclude.
Concurrency allocation clauses are valid. The prevention principle does not override express terms; the parties may agree whatever allocation of concurrent delay risk they wish.
Read the sourceWherever the contractual line falls, the dispute is decided on the records. Concurrency arguments collapse or succeed on the quality of the as-built evidence and the causal analysis built on it, and the party that can demonstrate what was actually driving completion, week by week, usually prevails.
- 01The as-built sequence of the works, assembled from contemporaneous progress records rather than reconstructed programme logic.
- 02Which activities were driving completion when each delay event took effect, not which were critical at contract award.
- 03The start, duration and effect of each employer event, tied to instructions, correspondence and site diaries.
- 04The contractor's own delay, recorded with the same candour; an analysis that conceals it will not survive scrutiny.
- 05Cost records granular enough to separate time-related loss caused by the employer event from loss that would have been incurred in any event.
Concurrency is argued as a point of law and decided as a question of fact. The doctrine occupies a few paragraphs; the evidence that proves or destroys true concurrency runs to thousands of documents: programmes, progress updates, site diaries, labour returns and correspondence. Most concurrency arguments fail not because Walter Lilly was misread but because the as-built record was never assembled with the discipline the causation exercise demands.
Meritus Via brings programme data, correspondence and project records into a connected evidence base. Specialist tools support the preparation and analysis; our practitioners test the sources, explain the method and form the conclusions. A partner directs the work within the agreed appointment.
- [1]Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32 (TCC, Dyson J).
- [2]Walter Lilly & Company Ltd v Mackay [2012] EWHC 1773 (TCC), Akenhead J at [370].
- [3]City Inn Ltd v Shepherd Construction Ltd [2010] CSIH 68 (Inner House, Court of Session).
- [4]De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC), Edwards-Stuart J.
- [5]North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744, Coulson LJ.
- [6]Society of Construction Law, Delay and Disruption Protocol, 2nd edition (February 2017), Core Principles 10 and 14.
The views expressed in this article are those of the author and are intended for general information only. They do not constitute legal advice and should not be relied upon as such. Specific professional advice should be sought in relation to any particular matter.
Discuss your position
Direct access to a partner. No intermediaries.