Skip to content
The Lock
Briefing

The Levy and the Locked Door

August 2026|7 min|6 parts
Key Takeaways
  1. KT.01The Building Safety Levy is not simply a new cost. Its enforcement mechanism is the completion certificate: unpaid levy, no certificate, no lawful occupation.
  2. KT.02Liability attaches to the client named in the building control application. On design and build procurement that is frequently the contractor, which puts the tax on a party that never priced it.
  3. KT.03Most live contracts contain no route to pass the levy on. The change in law provisions in JCT 2024 and NEC4 are switched on in the Particulars, and on the 2016 forms there is generally nothing to switch on at all.

Almost everything written about the Building Safety Levy has treated it as a tax question: what the rate is, which schemes are caught, how to model it in an appraisal. That is the smaller half of the problem. The levy is enforced by withholding the completion certificate, which means an unpaid tax now stops handover, stops occupation, and stops the revenue that was going to pay it. From 1 October 2026 a payment obligation owed to a local authority sits directly on the critical path, and the contracts that will have to absorb it were written before it existed.

PT.01

The mechanism, and the part of it that matters

10dwellings
Where the levy starts

The charge applies to building control applications made on or after 1 October 2026 for at least ten dwellings, or at least thirty bedspaces in purpose-built student accommodation, in England. Rates are set per square metre for each local authority area, and a site qualifies for the half rate only where at least 75 per cent of the land is previously developed.

The Building Safety Levy (England) Regulations 2025 come into force on 1 October 2026 and apply to England only.¹ The charge is calculated on chargeable floorspace at the rate published for the relevant local authority area, and those rates vary widely between areas. The half rate for previously developed land is narrower than it is usually described: the test is whether at least 75 per cent of the land to which the relevant planning permission relates was previously developed immediately before the relevant date, so a scheme with a substantial greenfield component pays in full.² Local authorities are the collecting authorities in every case, including where the Building Safety Regulator is the building control authority. Levy information is provided with the building control application and again at commencement, the collecting authority then issues either a levy liability notice or a notice of no charge, and payment must be made before completion of the works or occupation of the building, whichever comes first.³

The enforcement provision is the whole point. If the levy is unpaid, the completion certificate is withheld, the final certificate given by a registered building control approver is rejected, and a completion certificate application under the higher-risk buildings regime is rejected.⁴ There is no interest charge and no penalty regime anywhere in the regulations doing that work; the sanction is simply that the building cannot lawfully be occupied. A named client who disputes the assessment may request a review and appeal the review decision, but neither step opens the door: the certificate follows payment, and the argument about whether the sum was right happens either side of it.⁴ A tax has been converted into a condition precedent to completion.

The sanction is not a penalty. It is the door.

One qualification before relying on any of the detail. The Building Safety Levy (Amendment) (England) Regulations 2026 were still in draft in mid-August 2026, laid before Parliament and expressed to come into force on the same day as the principal regulations. They are corrective rather than substantive: they tighten the previously developed test, correct cross-references, tighten the spot check notification deadlines and clean up terminology. They do not change the rates, the thresholds, or the completion certificate lock.⁵ Anyone modelling a marginal brownfield site should nonetheless read the amended definition rather than the original.

PT.02

Who is the client?

Liability follows the client named in the building control application, and the regulations define who that is by reference to the type of application: full plans applications, initial notices, and higher-risk building applications each have their own rule.⁶ That is a building control concept, not a construction contract concept, and the two do not always identify the same party. On traditional procurement the employer is usually the applicant and the levy lands where commercial logic expects it. On design and build, and on the various contractor-led arrangements now common in residential development, the contractor frequently makes the application and is named as client. The result is a statutory liability for a tax assessed on the developer's floorspace, sitting on a contractor which priced the works and not the levy.

This is worth resolving deliberately rather than discovering at commencement. Two questions decide it: who is named as client in the application, and what the contract says about who bears statutory charges of this kind. Where the contract is silent, the party named on the application is the party the collecting authority will pursue, and any recovery from the other side is a contractual argument to be had afterwards, from the weaker position of having already paid.

PT.03

Is it a change in law?

The instinctive answer is that a new statutory charge introduced after the contract was made must be recoverable as a change in law. On most live contracts it is not. The JCT Design and Build 2016 form contains no general change in law provision entitling the contractor to additional payment; the closest Relevant Event, at clause 2.26.12, addresses the exercise of a statutory power and, under the standard Relevant Matters list, carries time rather than money.⁷ The 2024 edition introduced a Relevant Event at clause 2.26.8 and a Relevant Matter at clause 4.21.7 covering changes in law and the exercise of statutory powers, but JCT's own commentary records that these apply only where the Contract Particulars say so.⁸ NEC4 deals with changes in law through secondary Option X2, which is optional and frequently not selected.

So the analysis on any given project is short and unglamorous. Look at the date of the contract, look at the Particulars or the selected secondary Options, and look at the schedule of amendments. On a contract entered into before 2025 with no bespoke levy provision, the levy is an unallocated cost that will be borne by whoever the statute makes liable, and the arguments available afterwards are the difficult ones: implied terms, mistake, or a strained reading of a statutory power clause that was not written with a tax in mind.

For contracts being negotiated now the drafting point is simple and should not be controversial: state who is named as client for building control purposes, state who bears the levy, and state what happens to the completion date and to liquidated damages if a certificate is withheld because the levy has not been paid. Three sentences at tender stage prevent an expensive argument at practical completion.

PT.04

The race to 1 October, and what it is creating

Applications submitted before 1 October 2026 fall outside the charge, and the sector has responded exactly as expected: a concentration of building control applications submitted ahead of the deadline. Two consequences follow, and both will generate work for the people who assess claims.

The first is application quality. An application submitted early to beat a tax deadline is not always an application that is ready, and a rejected or invalidated application is a poor foundation for the argument that the scheme escaped the levy. Where the higher-risk building regime applies, the regulator's own data shows what marginal applications meet: eighteen per cent of gateway 2 decisions in the twelve weeks to 1 August 2026 were rejections.⁹ A firm which submitted early, was rejected, and resubmitted after 1 October has bought itself a levy liability and a professional negligence question about who prepared the application.

The second is the lapse rule, and it is the one being missed. Building control approval ceases to have effect if the work is not commenced within three years, and the regulations define what commencement means for that purpose.¹⁰ A scheme whose approval lapses has to apply again, and an application made on or after 1 October 2026 is chargeable whatever the date of the application it replaces. Schemes pushed into September 2026 to beat the charge, and then held back for viability or funding reasons, therefore re-enter charge in 2029 at whatever rate then applies. That is a contingent liability created this quarter which will be argued over three years from now, and it belongs in the risk register today rather than in a final account later.

PT.05

Non-payment as an act of prevention

The most interesting consequence is what happens where the levy is the employer's liability and the employer does not pay it. The works are complete, the certificate is withheld, and the building cannot be occupied. If practical completion or the release of retention is tied to a certificate the employer's own default has prevented, the contractor's argument is not a change in law argument at all: it is an impediment, prevention or default of the employer, which under the JCT Design and Build form is a Relevant Event at clause 2.26.6 and, unusually, a Relevant Matter at clause 4.21.5, so it carries both time and money.⁷ Where the employer is also levying liquidated damages for the resulting overrun, the prevention principle is squarely engaged.

The mirror image applies where the contractor is the named client and does not pay. There the withheld certificate is the contractor's own doing, and it will struggle to characterise the resulting delay as anything other than culpable. The consequence of the levy, then, is not merely a cost to be allocated. It creates a new species of completion dispute in which the identity of the payer determines who owns the delay, and that identity is fixed by a form filled in at building control application stage, often by a design manager, months or years earlier.

A tax that stops handover is a delay event with an invoice attached.

PT.06

What to capture now

Everything in this article is decided on documents which either exist or do not. The ones that matter are being created in the next six weeks.

The record to build before 1 October
  • 01The building control application itself, showing the date of submission and, critically, who is named as client. This single field determines statutory liability.
  • 02The levy information provided with the application and at commencement, and the collecting authority's liability notice or notice of no charge when it issues.
  • 03The contract date, the Contract Particulars entries for the change in law and statutory powers provisions, the selected secondary Options, and any schedule of amendments dealing with statutory charges.
  • 04The internal decision to submit early, its rationale, and the programme assumption for commencement, because the three-year lapse rule turns that assumption into a contingent tax liability.
  • 05Any rejection or invalidation of an application submitted before the deadline, with the reasons taken from the decision notice, and the resubmission date.
  • 06The site's previously developed status and the evidence for it, because the half rate turns on a 75 per cent threshold that the draft amendment regulations narrow further.
  • 07For schemes in charge, the levy sum, when it was demanded, when it was paid, and by whom, kept with the completion documentation rather than in the finance system alone.
The Meritus View

Our expectation is that the first levy disputes will not be about the tax. They will be about completion: withheld certificates, delayed handovers, liquidated damages running against a contractor which cannot obtain a certificate because someone else has not paid, and arguments about who was named as client on a form nobody treated as a commercial document at the time. The legal analysis in each case is short. The evidence is not, because it sits across the building control file, the contract particulars, the programme and the payment record.

Meritus Via assembles that evidence base at machine speed: application history, statutory correspondence, contract documents and programme sequence mapped and cross-referenced within hours of instruction, every conclusion traceable to source and every method disclosable. The construction of the contract and the opinion on entitlement remain where they belong, with senior practitioners, partner-led from first instruction through to testimony. We automate the preparation. Never the judgment.

References
  1. [1]The Building Safety Levy (England) Regulations 2025, SI 2025/1236, in force 1 October 2026 (England only); regulation 6 ("major residential development": at least 10 dwellings or at least 30 bedspaces in purpose-built student accommodation) and regulation 15 (charge to the levy).
  2. [2]SI 2025/1236, regulations 20 and 21 with Schedule 3: a previously developed site is one where at least 75 per cent of the land to which the relevant planning permission relates was previously developed immediately before the relevant date.
  3. [3]SI 2025/1236, regulations 37 to 40 (determination of levy liability, levy liability notice, notice of no charge) and regulation 24 (levy due date); Ministry of Housing, Communities and Local Government, Building Safety Levy: Guidance.
  4. [4]SI 2025/1236, regulations 58, 60 and 62 (withholding a completion certificate; rejecting a final certificate; rejecting completion certificate applications), and regulations 71 to 73 (request for a review, carrying out a review, appeal against a review decision).
  5. [5]Draft Building Safety Levy (Amendment) (England) Regulations 2026, laid before Parliament under section 120A(7) of the Building Act 1984 and expressed to come into force on 1 October 2026. Status as at 17 August 2026: draft.
  6. [6]SI 2025/1236, regulations 22 and 23 with Schedule 4 (liability of the named client, and the identification of the named client for full plans applications, initial notices and higher-risk building applications).
  7. [7]JCT Design and Build Contract 2016, clauses 2.26.6, 2.26.12 and 4.21.5.
  8. [8]JCT Design and Build Contract 2024, clauses 2.26.8 and 4.21.7, and JCT commentary on their application through the Contract Particulars; NEC4 Engineering and Construction Contract, secondary Option X2 (changes in law).
  9. [9]Building Safety Regulator, building control gateway 2 performance update, twelve-week rolling period to 1 August 2026.
  10. [10]Building Act 1984, section 32 (lapse of building control approval where work is not commenced within 3 years), and the Building Regulations 2010, regulation 46A (meaning of commencement for the purposes of section 32(6)).

The views expressed in this article are those of the author and are intended for general information only. They do not constitute legal advice and should not be relied upon as such. Specific professional advice should be sought in relation to any particular matter.

Discuss your position

Direct access to a partner. No intermediaries.

Discuss Your Matter
100GB+
Per matter. In hours.